SHAPE Village Reconstruction

 
 
 
 
 
   

 
The military authorities of SHAPE addressed several requests to the Host Nation in order to reconstruct SHAPE VILLAGE. After a feasibility survey requested by the Ministry of
 
 
 
Finances, the project was approved by the Council of Ministers on 14 Feb 2014.
The project aims the reconstruction of 600 new homes (300 apartments and 300 houses). It is established with the desire to fulfill the needs of the SHAPE community, as well as to build energy efficient homes and build adequate and comfortable homes in respect of the ecology. 

The reconstruction project is planned in 7 phases from December 2018 to May 2026, and we invite you to discover them below.


Phase 1: demolition of 84 apartments
When the mastery of works will be granted, the first phase will consist in the demolition of 7 buildings (84 apartments) in the 600 area (Roger, Stone and Saturne). The demolition will probably start as of 14 December 2018.
The loss of these apartments will be primarily articulated in line with the departures of tenants leaving SHAPE as well as tenants moving from the temporary apartments to their houses.


Phase 2: construction
Housing situation; 224 new homes to bring up the housing capacity to 740, knowing the maximum amount of "shapians’ family” is limited to 600. Remember the project aims a capacity of 600.

Phase 3: demolition
Demolition phase: demolition of 130 homes, to leave a capacity of 610 on the campus, knowing the maximum amount of "shapians’ family” is limited to 600.

Phase 4 : construction
Reconstruction phase: reconstruction of 235 homes to reach the total amount of 845 homes on base, knowing the maximum amount of "shapians’ family”/occupation is limited to 600.

Phase 5:demolition
Demolition phase; demolition of 194 homes, which decreases the amount of homes down to 651, but the occupation capacity remains 600.

Phase 6: construction
Reconstruction phase; construction of 141 homes to reach the amount of 792 on base, knowing the maximum amount of "shapians’ family”/occupation is limited to 600.
 
Phase 7: demolition
Final demolition phase in the 600 area were 192 old homes (12 A Bldg) will be destroyed to reach the goal of 600 new homes.
 